  MM PROJECT - Strengthened Community Management for Sustainable Water and Sanitation services at Tunguli in Kilindi District Council.
  Detailed Budget for ten months from April 1, 2018 to January 30, 2019.
S/N Budget Category No units Type  Unit  Type/frequency %age of MM support  Unit Cost (TZS)   Total Estimated Cost (TZS)   Grantee Contribution (TZS)   MM support (TZS) 
1 SALARIES AND WAGES                  
1.1 SAWA Manager  (4%) 1 person 10 Months 4%     5,402,430.00        54,024,300.00       51,863,328.00              2,160,972.00
1.2 SAWA Technical WASH Advisor   (3%) 1 person 10 Months 3%     4,826,333.33        48,263,333.33       46,815,433.33              1,447,900.00
1.3 SAWA Project Accountant       (2%) 1 person 10 Months 2%     2,208,000.00        22,080,000.00       21,638,400.00                 441,600.00
1.4 SAWA Project Officer     (2%) 1 person 10 Months 2%     3,150,000.00        31,500,000.00       30,870,000.00                 630,000.00
1.5 SAWA Project  M&E            (1%) 1 person 10 Months 1%     2,587,500.00        25,875,000.00       25,616,250.00                 258,750.00
  Salaries subtotal                  181,742,633.33     176,803,411.33              4,939,222.00
                     
2 SALARY BENEFITS (PPF(10% etc)                  
2.1 SAWA Manager  (4%) 1 person 10 Months 4%        540,243.00          5,402,430.00         5,186,332.80                 216,097.20
2.2 SAWA Technical WASH Advisor   (3%) 1 person 10 Months 3%        482,633.33          4,826,333.33         4,681,543.33                 144,790.00
2.3 SAWA Project Accountant       (2%) 1 person 10 Months 2%        220,800.00          2,208,000.00         2,163,840.00                   44,160.00
2.4 SAWA Project Officer     (2%) 1 person 10 Months 2%        315,000.00          3,150,000.00         3,087,000.00                   63,000.00
2.6 SAWA Project  M&E            (1%) 1 person 10 Months 1%        258,750.00          2,587,500.00         2,561,625.00                   25,875.00
  Salary benefits subtotal                    18,174,263.33       17,680,341.13                 493,922.20
                     
3 OPERATIONAL COSTS                  
3.1 Office Rent 1 item 10 Months 2%     1,777,200.00        17,772,000.00       17,416,560.00                 355,440.00
3.2 Consumables (stationeries and photocopies) 1 item 10 Months 5%        700,000.00          7,000,000.00         6,650,000.00                 350,000.00
3.3 Utilities , water, electricity  1 item 10 Months 5%        350,000.00          3,500,000.00         3,325,000.00                 175,000.00
3.4 Office cleaning services and security 1 item 10 Months 5%        300,000.00          3,000,000.00         2,850,000.00                 150,000.00
3.5 Postage charges including transportation 1 item 10 Months 5%        100,000.00          1,000,000.00            950,000.00                   50,000.00
3.6 Communication charges ( Internet , telephone) 1 item 10 Months 10%        350,000.00          3,500,000.00         3,150,000.00                 350,000.00
3.7 Others ( bank charges, 1st Aid kit etc) 1 item 10 Months 0%        100,000.00          1,000,000.00         1,000,000.00                                -  
   Operation cost subtotal                    36,772,000.00       35,341,560.00              1,430,440.00
                     
5 ACTIVITY COSTS (Include; trainings, awareness, capacity building activities e.t.c)                  
5.1 Specific objective No.1: Engage Kilindi and Tumguli community in project planning and implementation                   
5.1.1 Inception workshop  at at the ward   level  including district representatives to share SAWA/MM project plan and Budget and develop a joint plan for implementation      
  Transport reimbursement to district staff 3 People 2 Trips 100%          20,000.00             120,000.00                          -                   120,000.00
  Night allowance for one day for Kilindi Staff 3 People 1 day 100%          60,000.00             180,000.00                   180,000.00
  Lunch and refreshment 41 People 1 Plates 100%          10,000.00             410,000.00                          -                   410,000.00
  Stationeries 40 People 1 Day 100%            3,000.00             120,000.00                          -                   120,000.00
  Per diem for SAWA Dar es Salaam 2 people 3 Days 100%          80,000.00             480,000.00                          -                   480,000.00
  Mileage  reimbursement ( Dar -Kilindi-Dar) 2 trips 400 km 100%            2,000.00          1,600,000.00                          -                1,600,000.00
  Sub total                      2,910,000.00                          -                2,910,000.00
                     
5.1.2 Conduct village general assembly to share project plan and budget ( budget not required)      
                     
5.1.3 Establishment of community management entity (COWSO) as per national guidelines      
  Conduct two days workshop to facilitate developmen of COWSO consttitution      
  Perdiem for District staff 3 People 2 days 100%          60,000.00             360,000.00                          -                   360,000.00
  Transport from to district 3 staff 3 People 2 trips 100%          10,000.00               60,000.00                     60,000.00
  Lunch and refreshment for participants 30 People 2 days 100%          10,000.00             600,000.00                          -                   600,000.00
  Per diem for SAWA headquarter staff 2 people 3 Days 100%          80,000.00             480,000.00                          -                   480,000.00
  Mileage reimbursement ( Dar -Tunguli-Dar) 2 trips 400 km 100%            2,000.00          1,600,000.00                          -                1,600,000.00
  Printing and photocopies of materials and report 1 item 10 bundle 100%            5,000.00               50,000.00                          -                     50,000.00
  Sub total                      3,150,000.00                          -                3,150,000.00
                     
  Conduct three days training to equip COWSO leaders with financial management, leadership and operation and maintanance skills                  
  Perdiem for District staff 1 People 2 days 100%          60,000.00             120,000.00                          -                   120,000.00
  Transport from to district 3 staff 2 People 2 trips 100%          15,000.00               60,000.00                     60,000.00
  Lunch and refreshment for participants 25 People 3 days 100%          10,000.00             750,000.00                          -                   750,000.00
  Per diem for SAWA headquarter staff 2 people 3 Days 100%          80,000.00             480,000.00                          -                   480,000.00
  Mileage reimbursement ( Dar -Tunguli-Dar) 2 trips 400 km 100%            2,000.00          1,600,000.00                          -                1,600,000.00
  Printing and photocopies of materials and report 1 item 10 bundle 100%            5,000.00               50,000.00                          -                     50,000.00
  Sub total                      3,060,000.00                          -                3,060,000.00
5.2.2 Community care takers visit Morogoro for two days to lean how to manufacture  rope pump parts      
  Transport for participants from  to Morogoro 5 People 2 trips 100%          10,000.00             100,000.00                          -                   100,000.00
  Perdiem for two days 5 People 2 days 100%          50,000.00             500,000.00                          -                   500,000.00
  Pump mechanics training fee for 2 days 2 People 2 trips 100%          80,000.00             320,000.00                          -                   320,000.00
  Stationeries 20 People 1 Item 100%            3,000.00               60,000.00                          -                     60,000.00
  Sub total                         980,000.00                          -                   980,000.00
                     
  Sub total for Specific Objective 1                    10,100,000.00                          -              10,100,000.00
5.2.4 Conduct  one  day Capacity building  session of Sub Village teams on data collection       
   stationeries 30 people 1 day 100%            3,000.00               90,000.00                          -                     90,000.00
  Lunch and Refreshments 35 People 1 day 100%          10,000.00             350,000.00                          -                   350,000.00
  transport reimbursement for DHO 1 People 2 Trips 100%          10,000.00               20,000.00                          -                     20,000.00
  District staff perdiem 1 people 1 days 100%          65,000.00               65,000.00                          -                     65,000.00
  SAWA staff perdiem 2 people 2 days 100%          80,000.00             320,000.00                          -                   320,000.00
  Mileage reimbursement ( Dar -Tunguli-Dar) 2 trips 400 km 100%            2,000.00          1,600,000.00                          -                1,600,000.00
  Sub total                      2,445,000.00                          -                2,445,000.00
  Preparation of sanitation and hygiene training material in line with NSC tools and fit to local environment in data collection, triggering (animators), technologies.      
  Sanitation register  11 pcs 1 pc 100%            5,000.00               55,000.00                          -                     55,000.00
  Printing of training materials 11 Manuals 1   100%            5,000.00               55,000.00                          -                     55,000.00
  Sub total                         110,000.00                          -                   110,000.00
  Conduct pre-triggering and triggering sessions at sub village level.      
  Two facilitator from DHO offiice Kilindi 2 people 2 village 100%          65,000.00             260,000.00                          -                   260,000.00
  Facilitators transport reimbursement( District) 2 people 2 session 100%          20,000.00               80,000.00                          -                     80,000.00
  Facilitators transport reimbursement( at ward level) 4 people 2 session 100%          10,000.00               80,000.00                     80,000.00
  Purchasing of triggering materials 11 subvillages 1 frequency 100%          20,000.00             220,000.00                          -                   220,000.00
  Perdiem SAWA facilitators 2 people 3 days 100%          80,000.00             480,000.00                          -                   480,000.00
  Mileage reimbursement ( Dar -Tunguli-Dar) 2 trips 400 km 90%            2,000.00          1,600,000.00                1,440,000.00
                         2,720,000.00                2,560,000.00
5.3 Post-triggering activities                  
5.3.1 Follow up on latrines construction and hygiene practices.                  
  Transport reimbursement for ward health officer 1 persons 6 frequency 100%          20,000.00             120,000.00                          -                   120,000.00
  Data collectors updating register 22 persons 4 frequency 100%          10,000.00             880,000.00                          -                   880,000.00
  Local facilitator 1 people 6 frequency 100%          20,000.00             120,000.00                   120,000.00
  Data consolidation  on quarterly basis  3 people 4 frequency 100%          10,000.00             120,000.00                          -                   120,000.00
  Monitoring at village level 4 people 6 days 100%          10,000.00             240,000.00                          -                   240,000.00
  Per diem for SAWA  2 Person 2 frequency 100%          80,000.00             320,000.00                          -                   320,000.00
  mileage claim (Dar -Tunguli-Dar) 4 Trips 400 kms 100%            2,000.00          3,200,000.00                          -                3,200,000.00
                         5,000,000.00 0              5,000,000.00
   Facilitate Internal and external ODF verification exercises.                  
  Transport reimbursement for district and region team 4 People 2 days 100%          30,000.00             240,000.00                          -                   240,000.00
  Perdiem for district and region team 5 People 2 days 100%        100,000.00          1,000,000.00                          -                1,000,000.00
  Refreshment for ward and village team 10 People 2 days 100%          10,000.00             200,000.00                          -                   200,000.00
  Sub total                      1,440,000.00                          -                1,440,000.00
                     
  TOTAL PROJECT COSTS                    28,678,584.20       28,678,584.20  
                     
  UK paud 1=   2900                             9,889.17                9,889.17                                -  